Dear Homeowner, 

Please see below for this week's landscaping updates that will be completed, weather permitting.

General Update: 

The poor weather conditions have pushed many of the items into next week. Thank you for your patience and cooperation during this time. Thankfully the forecast next week is looking sunny!

Price Lane

      • Landscapers will follow through once the ground has dried up.

Paisley Drive

  • Parging will be starting.
  • Once the ground dries, landscapers will be through to back fill garage pads and start rough grading.

Parker Loop

  • Once the ground dries the landscapers will finish all remaining items left. Please make sure to water your grass every day.