Dear Homeowner,
Please see below for this week's landscaping updates that will be completed, weather permitting.
Chokecherry Lane (Single Family Homes)
- Exterior Painting and parging will continue next week.
- Rough grading and landscaping will continue, please make sure that items left in the yards are cleaned up.
- The parking pads that were recently poured can be parked on in 3 weeks.
Chokecherry Place (Duplexes - Front Drive)
- Continue to water any fresh sod that has been installed.
Chokecherry Close (Duplexes – Front Drive)
- We are starting our rough grading on your homes, please ensure that personal items left in the yards are cleaned up.
Chokecherry Place (Duplexes - Rear Lane)
- Parking pads are 1 week away from being able to park on.
- Rough grading has started and the garages have started to be worked on
Chokecherry Common (Move up homes)
- Exterior painting on the house should be completed this week.