Dear Homeowner, 

Please see below for this week's landscaping updates that will be completed, weather permitting.

Concrete Updates

Garbage garage on SW corner.

Rough Grading

Units 112-119 start work on grading for patios/sidewalks/block wall.

Next Week (June 14-18):

Units 112-119 ongoing work on grading.

Landscaping Updates

Units 1, 2, 3 landscaping completed.

Next Week (June 14-18):

Units 1, 2, 3 fencing completed.