Dear Homeowner,
Please see below for this week's landscaping updates that will be completed, weather permitting.
Concrete Updates
Block #16, Units 102-111: Block wall prep (about 1 week)
Block #17, Units 57-66: Block wall prep (about 1 week)
Block #20, Units 47-56: Sidewalks/patios done this week
Landscaping Updates
Block #16, Units 102-111: Landscaping is about 2 weeks away, weather permitting.
Block #17, Units 57-66: Landscaping is about 2 weeks away, weather permitting.
Block #20, Units 47-56: Landscaping is about 2 weeks away, weather permitting.
Grading Updates
Block #16, Units 102-111: Grading for block wall starting end of June
Block #17, Units 57-66: Grading for block wall starting end of June