Dear Homeowner,
Please see below for this week's landscaping updates that will be completed, weather permitting.
General Update:
- All exterior concrete work will be on hold for the 2019 season and will resume after the May long weekend of 2020 due to freezing overnight temperatures.
- Weather permitting, black dirt will be installed next week from 699 - 661 Eagleson Cres and landscape completed.
- Pre grades will be complete along Edgemont Blvd.