Please see below for this week's landscaping updates that will be completed, weather permitting.

This is the final landscape update for the 2020 season. Landscaping updates will commence after the 2021 May long weekend.

Concrete Flatwork

n/a

Front Landscaping

Waiting for grade certificate (1 week) and grade approval (1 week), after both landscaping will commence.

4216, 4218 Chichak Close

4329, 4331 Cooke Lane

4132 Chappelle Green

3407 Craig Landing 

Rear Landscaping

3407 Craig Landing (waiting for grade certificate (1 week) and grade approval  (another week) and then landscaping will commence)

Rough Grading/ Top Soil

4118, 4120, 4126, 4130 Chappelle Green 

 