Dear Homeowner,
Please see below for this week's landscaping updates that will be completed, weather permitting.
This is the final landscape update for the 2020 season. Landscaping updates will commence after the 2021 May long weekend.
Concrete Flatwork
n/a
Front Landscaping
Waiting for grade certificate (1 week) and grade approval (1 week), after both landscaping will commence.
4216, 4218 Chichak Close
4329, 4331 Cooke Lane
4132 Chappelle Green
3407 Craig Landing
Rear Landscaping
3407 Craig Landing (waiting for grade certificate (1 week) and grade approval (another week) and then landscaping will commence)
Rough Grading/ Top Soil
4118, 4120, 4126, 4130 Chappelle Green