Dear Homeowner, 

Please see below for this week's landscaping updates that will be completed, weather permitting.

Cooke Lane

  • Finished rough grades. Properties with black dirt down will be landscape complete within the next week.
  • Parging: any outstanding properties will be completed in Spring 2020.
  • Concrete: any outstanding properties will be completed in Spring 2020.
  • Exterior paint is wrapped up for the year due to temperature. We will start again in June 2020.

Coughlan Green

  • Finished rough grades. Properties with black dirt down will be landscape complete within the next week.
  • Parging: any outstanding properties will be completed in Spring 2020.
  • Concrete: all properties are complete.
  • Exterior paint: any outstanding properties will be completed in Spring 2020.

Chappelle Green

  • Finished rough grades. Properties with black dirt down will be landscape complete within the next week.
  • Parging: any outstanding properties will be completed in Spring 2020.
  • Rear concrete pad will be poured for 4032 in June 2020.
  • Exterior paint: any outstanding properties will be completed in Spring 2020.

Chichak Close

  • Rough grading and landscaping is finished for 2019. Any outstanding properties will be completed in Spring 2020.
  • Parging: any outstanding properties will be completed in Spring 2020.
  • Concrete is complete for 2019.
  • Exterior paint: any outstanding properties will be completed in Spring 2020.