Dear Homeowner,
Please see below for this week's landscaping updates that will be completed, weather permitting.
May 28 Note: The rain that we have experienced over the previous week has delayed the updates and greatly saturated the ground. This is a benefit to your property as it ensures that the ground has compacted to reduce movement with the yardwork. This means your landscaping and concrete will have a lesser chance of settlement.
Concrete Flatwork
sidewalks, driveways and garage/parking pads
521/523 Paterson Way (rear pads)
541/542 Paterson Way (front sidewalk and rear pads)
517, 519, 532, 540 Paterson Way (front sidewalk and rear pad)
Next Week (June 7 - June 11):
525/527 Paterson Way (front sidewalk/rear pad)
2265, 2267 Price Land
3279, 3311, 3319, 3367, 3373 Parker Loop
Rough Grading
no updates this week.
Next Week (June 7 - June 11):
517, 519, 521/523, 532, 540, 541/543 Paterson Way
Front Landscaping
521/523, 530, 536, 538, 542, 558 Paterson Way
Next Week (June 7 - June 11):
517, 519, 532, 540, 541/543 Paterson Way
Rear Landscaping
No updates this week.