Order Task Duration Notes
1 Exterior Paint 1-3 days Can be completed once overnight temperature is consistently above 10 Celsius.
2 Pre-Grading 2-3 days Roughly shape lot to help with drainage and settlement.
3 Exterior Concrete 1 week Access will be comprised while pouring driveways and sidewalks. Do not drive on fresh concrete for 1 month.

3(b)

*If Applicable

Front Steps 1 days Permanent front steps will be built on rear lane homes after concrete has cured for 24 hrs.
4 Rough Grade 2-3 days Finalize Grading of lot.
5 Rough Grade Approval 1-2 weeks City of Edmonton must come out and inspect the rough grade of each home. Landscaping can begin after home passes.
6 Parging 1-2 days Decorative Concrete that covers exposed foundation.
7 Rear Deck Upgrade 1-2 days Installation will compromise rear access.
8 Top Soil 1-2 days Top soil will be laid after Rough Grade Approval.
9 Landscaping 2-3 days Sod, Shrubs and Mulch installed. Be sure to water twice per day.
10 Garage Install 2-3 weeks Only applicable on Rear Lane homes. Construction of the garage will begin roughly 3 weeks after the pad has been poured to allow concrete to cure.

11

*If applicable

Final Grade Approval 1-2 weeks Only applicable if rear landscaping was purchased through Brookfield. The City will come and inspect the property once everything is complete.

Subscribe for Weekly Updates!